postheadericon VMware vSphere on IBM BladeCenter H – (Part 2 of 2)

Yes, finally! It's been like what? Five months?! Well, the delay in publishing this part was mainly because of the delay in certifying the new IBM HX5 blades on vSphere. It's a quite long process that you can read about it here, but the good news is that the hardware is finally on VMware's HCL, and that I can comfortably blog about the subject now without causing any confusions to the readers.

Before we dig deep into the new designs, I'd like to mention some minor changes in the diagram.

Updated Diagram

I've included the old configurations along with the new ones in one updated PDF. The main difference now is that I'm using normal pages for showing each configuration. In the old version I used the layers to show and hide the configurations as you select them. I thought now that using separate pages for different diagrams would ease the process of browsing through the configurations, and to tell you the truth, to reduce also the high complexity of designing the diagram. It's a crazy process to keep track of all these layers in Visio especially when we are talking about more than 7,000 shapes floating on the same design area!

Now let's get down to business.

Configuration (5) – HX5:

This is the Big Blue's latest two-node blade technology. I emphasized on the "two-node" here because it's the only configuration certified to run with vSphere as of the time of writing these lines. Please note that you can use up to 4 nodes with the HX5 but this won't be supported by VMware. When we talk about two nodes here we mean the following:

  • Having the base blade (CPU + Mem + HDD) (+Plus+) the MAX5 expansion try to scale up more memory for the blade.
  • Having the base blade (again CPU + Mem + HDD) (+Plus+) another similar expansion board to scale all the blade components, that's 4 x CPUs + 2 x Memory modules + 2 x IO expansion cards.

As you will see in the diagram, I chose the second option to talk about.

Now, what do we have here? it's simply the redundancy at its best! We can place our networks here freely with full redundancy as you see in the layout of the vNICs. For example, if we have a failure in the CFFh expansion card on any of the two nodes, we will still be able to flow the traffic without any issues on the other CFFh card. Same thing holds true for the on-board ports, if for any reason one of these posts fail, the traffic will flow on the other node's board.

Apart from that, I'm introducing here the DMZ networks for the first time. Most of the enterprises prefer to separate the DMZ networks/servers on different chassis for security reasons. While this is a valid decision, we can have with this blade configuration a workaround for organizations that are less paranoid about the DMZ security, yet with good isolation. Let's see how this is done in details:

  • For the networks, we have two dedicated blade switches that will be uplinking *only* to the corp DMZ switches (in this case Bay 9 & 10). This means we will have no traffic following from either the internal networks or the VMkernel networks. Same thing for the blade ports, you will always have the NICs 4, 5, 10 and 11 dedicated for the DMZ networks and running in full performance and redundancy.
  • For the SAN, we can also ensure that we have a dedicated HBAs as well as an isolation. The uplinks to the SAN switches will be segmented across the two bays 3 and 4, and connected directly/physically to the appropriate SAN fabrics.

Configuration (6) – Virtual Fabric:

Before we start with this configuration, I would like to state that I am not quite sure whether these Emulex Virtual Fabric Adapters (VFA) are supported by VMware or not. While I can't see them clearly on the HCL with the name VFA, I can see some Emulex documents saying that they are. Of course the reference here should be always the VMware HCL itlself, not anything else, but I will double check on that and update this post later. With that said, please refer to this configuration carefully and make sure to confirm this point before engaging with any vSphere design around it.

Now let's dig deep into this cool technology. IBM simply has this Virtual Fabric concept of slicing your CFFh expansion card into 8 different ports. This doesn't only mean that you have the flexibility to adjust the speed, but also the protocol. For example, you can choose to use either Ethernet, Fibrechannel, FCoE or even iSCSI with hardware initiators.

In our case here I used only Ethernet as the protocol for these ports, and then sliced them into 8 different vNICs with various link speeds. Perhaps a screenshot from the diagram would make things more clear.

As you see, we set the bandwidth for the SC to 1GB since we normally don't require high BW for management, while we set 3GB and 5GB link speed for the Fault Tolerance and VM Networks respectively. By default these ports are set to 2.5GB ( 4 x 2.5GB = 10GbE into two ports), but you have the full flexibility to change that as you see.

Configuration (7) – CNA:

A very simple design to wrap up this series with. It's the traditional CNA (oh yeah, it's a common and traditional technology now!). As you see in the diagram, we have here a CFFh expansion card, and it has got four ports:

  • Ethernet ports: that's 2 x 10GbE Ethernet ports for the networking traffic. We will treat them here normally as we treat any 10GbE port. We will slice them via the vNetwork traffic shaping in vSphere to achieve the bandwidth that we want.
  • FibreChannel ports: that's 2 x HBA ports for SAN traffic. Instead of going into the traditional Bay 3 & 4 as we've see across the whole series and configurations, this time the traffic is multiplexed and pushed to the Nexus 4000 blade switches.

Did I just say Nexus 4000?! yep, that's a specially developed Nexus switches by Cisco to be used only/currently with the IBM BladeCenter H/HT. But here is the catch, you will still need to have the Nexus 5000 switches to segregate the FCoE traffic coming from the Nexus 4000 and then forward the network and FC traffic to the existing LAN and SAN respectively. Of course we should have redundancy here at all layers. In the BCH we have two Nexus 4000 sitting in bays 7 and 9, while we have two Nexus 5000 switches in the back end.

Now what?

Well, as much as I worked really hard in this series to come up with different kind of configurations and design scenarios, as much as I enjoyed it! Now I need to move on to another vendor, but without all these mad options. I initially was planning to jump straight to the HP realm, however, i found myself involved in two different Cisco UCS vSphere designs lately, so it would make much sense to me if I blogged about this platform now. Don't take my word for it though, I might surprise with a Dell or Fujitsu series, who knows?!

  • Share/Bookmark

postheadericon vSphere In A Box: Part(2): Putting the pieces all together

The response to my previous post has been unreal! The amount of tweets, ping backs, hits, linking, emails was quite amazing. I have to admit, I didn't expect to see that much of interest in the subject, but thanks to everyone who participated in promoting this idea on twitter and the blogosphere.

In the second part of this series we will spice things up a bit and explore through the following video many aspects of the idea we've talked about. Following to that an important screenshots and some considerations you should be aware of before and after implementing this in your lab.

What you'll see in this video:
1- Deploy a thin-provisioned vESX(i) VM from a template.
2- Check the required configuration parameter on the vESX to run nested VMs.
3- Customizing the new vESX server (assign password, set a static IP, put the DNS config ..etc)
4- Add the vESX to an existing HA Cluster.
5- Test the vMotion within the same cluster and across deferent clusters in the datacenter.
6- Add the required configuration parameter on the nested VM for enabling the FT.
7- Enable the FT and test the failover across deferent vESX servers.

 

A Quick note on the hardware used:
Technically speaking, only one server can be used in this whole setup. What is deferent in my setup (as you saw in the diagram) is that I use an external iSCSI array (the CLARiiON AX4) for hosting the vESX VMs. I just needed the flexibility to have them on an external storage to share them later on with other servers, but it is not a requirement. You can simply use the internal storage of the pESX server to host your vESX and you will still have everything you see in the video. As far as the shared storage for the vESX servers is concerned, you can use the Celerra VSA. In my case I use the Celerra only for the SRM labs to do the replication trick. Other than that, I use the OpenFiler as my shared storage for the nested VMs.

 

Two things to be set on the pESX hosts:
1 – Increase the number of ports on your pESX vSwitch to accommodate the increased number of connections required by your vESX VMs.

2 – Enable the "Promiscuous Mode" on the vSpwitch

 

The configuration parameters on the Virtual Machines are as follows:
1 – The virtual ESX (vESX) host: monitor_control.restrict_backdoor = TRUE

2 – The nested VM: replay.allowBTOnly = TRUE

 

The iSCSI vSwitch on the pESX host bound to vmnic1 (phisical NIC 2) and connected to the EMC CLARiiON AX4 iSCSI array

 

The vMotion internal vSwitch on the pESX host

The Fault Tolerance internal vSwitch on the pESX host

The thin-provisioned ESX(i) size on disk (475MB) + the memory swap:

The thin-provisioned ESX(i) size on disk(3.5GB) + the memory swap:


Other considerations and GOTCHAs:
1 – When enabling the FT, make sure you have your VMs powered off, even if they have eager zeroed disks, I used to get some errors when the VMs were powered on while enabling FT.

2 – Sometimes the network card order and numbering could be confusing. For example, in the vESX VM, you will have the NICs order starting from 1 to 10, but in the actual vESX network configuration tab, you will find the NICs starting from 0 and counting towards 9. This could be confusing when mapping your vnics to the pESX host vSwitches, like the VMotion internal switch, the FT internal switch and so forth. Just make sure you count the nics order accurately.

3 – Deploying vESX from templates may be cool and fast, but it could a bit challenging sometime in troubleshooting the network related issues. The reason behind that is the fact that all the network cards will have the same MAC address, or worst, the Port Groups like (VMotion) could have the same MAC address even if you completely remove the vnics and created brand new ones. The work around for that is to create the vESX template, and then remove all the NICs form it. When you deploy a new vESX, you can just add the new nics as you like, and by that you'll have a new MAC addresses. Beside that, you may need to add a new VMkernel network for the VMotion, and then remove the old one. Of course you may be thinking that deploying a brand new vESX would be easier, you are right, but with the scripting everything could be automated. I will try to write a PS script to automate this network changes/settings and post it here later on.

  • Share/Bookmark

postheadericon UPDATE: Intel Nehalem & VMware ESX4 will soon rock our virtual world!

Bingo! Just 3 hours after my last blog post, there was a live seminar from Intel with IBM, VMware & Microsoft regarding the new 5500 microprocessor! In the IBM presentation they announced the HS22 that I talked a bout ;) and in VMware they elaborated more on the integration and benefits with the new 5500 architecture, with emphasizing on the fact that the ESX4 will be the hypervisor that will get the most out of this next-gen processor capabilities.

You don’t want to miss this compact, yet great presentations:
http://www.intel.com/business/xeon/seminar.htm

Happy viewing!

  • Share/Bookmark

My name is Hany Michael and I’m a Senior Consultant at VMware. I blog about various topics ranging from the core vSphere technologies all the way to the vCloud based products. (Read more)
Disclaimer
Any views or opinions expressed on this blog are strictly my own and not the opinions and views of my employer.